Parliament sought to level the playing field by introducing statutory and obligatory adjudication.At the risk of being simplistic, a construction contract should set down a payment procedure, which should be followed when seeking payment. ‘Smash-and-grab’ adjudications can be commenced when a payment application and the relevant payment notices have not been issued in time. A successful ‘smash-and-grab’ adjudication entitles the contractor, subcontractor or consultant to paymen t of the full amount that they set out in their application, whether or not that sum was an accurate reflection of the value of work performed. It is very difficult to feel much sympathy for employer or main contractor whose competence is so lacking that they fail to comply with what is generally a simple payment procedure. Whilst it may be frustrating for an employer, the economic implications for a contractor can be drastic. No payment received, no subcontractors paid, no further works capable of being performed and potential insolvency for the contractor. Over the years, there have been concerns raised by main contractors/employers as to the ‘fairness’ of ‘smash and grab’. The answer to that one is simple: Issue a payment/valid pay less notice within time. In November 2018, the Court of Appeal gave judgment in S&T (UK) Limited v Grove Developments Limited, concerning a ‘smash-and-grab’ adjudication on an interim application for payment. In this case, however, the court held that the paying party could commence its own ‘true value’ adjudication to decide the true amount of the application in question, based on its merits. It also held that the paying party did not have to wait until the next payment application or assessment to commence such an adjudication, as had been found in an earlier case.
There was much speculation in the construction press as to whether this judgment meant the end of ‘smash-and-grab’ adjudications.In February 2019, the Technology and Construction Court issued its judgment in the case of M Davenport Builders Ltd v Greer & Anor, which is believed to be the first case applying the principles from the Grove case. In this case, the contractor Davenport commenced a ‘smash-and-grab’ adjudication against Mr and Mrs Greer in relation to its final account, and won, meaning it was entitled to £106,160.84 plus interest. However, rather than pay up, the Greers commenced their own true-value adjudication six days after the above adjudicator’s decision. Then Davenport commenced enforcement proceedings in the Technology and Construction Court (“TCC”) to enforce the first adjudicator’s decision. Before the TCC hearing, the adjudicator in the second adjudication issued his decision, which was to the effect that no sum was payable by the Greers to Davenport. The Greers, logically, wanted to set off the second adjudicator’s decision on the ‘true value’ of the final account against the first ‘smash-and-grab’ decision, which was in the contractor’s favour, saying as a result that nothing was due to Davenport. I say logically, but again remind you of the purpose of adjudication…to help with the liquidity of the contractors and subcontractors when faced with obstructive behaviour by the employer/main contractor. The key issue for the court at the enforcement hearing was whether, in light of the case law, the Greers could rely upon a claim to set off, given that they had not first complied with the ‘smash-and-grab’ decision. If they could, then it would mean they did not have to pay Davenport. It would also mean, arguably, that main contractors/employers would be given a backdoor method of delaying payment. The judge in Davenport considered and applied the judgment made in the Grove case and found that:
- Although Grove was concerned with an interim payment application, the principles applied equally to final accounts.
- The judgment in Grove was “clear and unequivocal” in stating that a party must pay the monies due under a smash-and-grab adjudication decision before it can commence a true-value adjudication.
- A party must pay the monies due under a smash-and-grab adjudication decision before it can rely upon a subsequent decision in a true-value adjudication.
Griffin Law is a dispute resolution firm comprising innovative, proactive, tenacious and commercially-minded lawyers. We pride ourselves on our close client relationships, which are uniquely enhanced by our transparent fee guarantee and a commitment to share the risks of litigation. If you have any specific questions regarding a dispute, please email justice@griffin.law or call 01732 52 59 23.